Calendar Event enables you to specify the recurring execution of process flow between the specified dates in conjunction with a specified calendar.

You will find a pre-bundled calendar event (Outbound_Queued_Event) to manually resend the queued outbound including FA, if it is stuck in the queue. You can activate or trigger this event to run the stuck transactions by right-clicking the event and select Trigger Now option.

To create a Calendar Event

  1. Click Configure > EVENTS > Calendar Event.



  2. Click CREATE Calendar Event.
  3. Type the name and description of the new Calendar Event in the Name and Description textboxfields respectivey.



  4. Click to select the date of which event will start triggering in the Event Start Date. The date must be in MM/DD/YYYY format. 
  5. Select the start time from the Time drop-down list in hh:mm format when the event will start triggering.
  6. Click to select the date of which event will stop triggering in the Event Expiry Date. The date must be in MM/DD/YYYY format.
  7. Select the stop time from the Time when the event will stop triggering.
  8. Select the days on which event should fire from the Firing Days.

    Days

    Description

    All Days

    The event will fire on all days (Mon to Sun) of the week.

    Business Days

    The event will fire from Monday to Friday excluding holidays.

    Week Days

    The event will fire from Monday to Friday even if there are any holidays.

    Note

    Business days can be configured by setting the value for the property org.quartz.scheduler.bCalendar. The following table explains what can be the default and possible values for this property.

    Value

    Specifies list of holidays of year

    Default value

    01/15/2007,02/19/2007,05/28/2007,07/4/2007,09/3/2007,10/8/2007,11/22/2007,12/25/2007

    Possible value

    Any date in mm/dd/yyyy format.

    Value description

    These days are assumed as holidays in Adeptia Connect calendar. If a Calendar Event is scheduled to be fired on Business Days, the process will not be fired on days specified in this property.

    To configure this property:

    1. Click Configure > Developer Studio > Proceed. 

    2. On Adeptia Suite home page, click Administer > Setup> Application Settings > Update System Properties > Services > Business Calendar.

    3. Update the Default value as required.

    4. Restart the Connect Server.


  9. Define the frequency of execution in the Firing Schedule. For information about Firing Schedule, click Help or refer to Cron Expression.

  10. Expand Advanced Properties to view the advanced properties of an Calendar Event.



  11. Type the email id in the Notification Receiver Email-ID(s) (comma separated) to receive error emails related to this Calendar event.
  12. Select Trigger in Sequence check box to trigger the associated process flow in a sequential manner. If you do not select the Trigger in Sequence check box then the associated process flow will trigger concurrently.

  13. If you want to enable misfire handling for your Calendar event then, select the Run Once option from the Action on Misfire Event drop-down list field. If you do not wish to enable misfire handling for your file event then, select the Ignore Misfire option.

    Info
    The Run Once option will run only one collective instance of all the misfires for a particular event. Whereas the Ignore Misfire option will not run a misfired event.


  14. Select the Project from drop-down list of the Project field.

  15. Click Save.