  1. Log into the Adeptia Suite with the admin or with the User who is the owner of the project.
  2. Click the Developer tab and then click Projects menu. All the projects are displayed (Figure 676).

    Figure 676: Projects Manage page

  3. On the Manage Project screen, click the Actions Image Removed Image Added icon of project, which you want to check-in. The list of possible actions is displayed (see figure below).

    You can also right-click the project row to view the actions that you can perform on the selected project (Figure 677).

    Figure 677: Actions menu on Project Manage page 

  4. Click Check-in to share the project. A confirmation message is displayed (see Figure 678).

    Figure 678: Application Message 

  5. Click Yes to Check-in the project. Depending upon on the number of activityactivities, sharing may take a few minutes. When all the activities of the selected projects is completedproject(s) are complete, a confirmation message is displayed (see Figure 679).

    Figure 679: Status Application message 

  6. Click OK to close this dialog box.
  7. Once the project is Checked in, a version number is assigned to the activities of the Project and icon to depict synchronization status is also placed with activity name (see Figure 680).


Figure 680: File Event Manage page


The icon depicts that the activity has been check-in and in sync with the copy of this activity in SVN server.

...