In this stage, it is necessary to analyze the existing AIS infrastructure and configuration.
Following the analysis report, recommendations can be made regarding the appropriate infrastructure for Adeptia Connect (clustered or non-clustered).
...
Provide a detailed explanation of the migration process to the client
...
E.g. - A client named ABC currently has the following AIS setup in place.
TEST (Kernel & Webrunner on Same Instance) Non-Clustered | QA (Kernel & Webrunner on Same Instance) Non-Clustered | PROD (Kernel & Webrunner on Same Instance) Non-Clustered |
---|---|---|
|
|
|
Given the existing AIS infrastructure, Discussion with the Client, and data transaction volume, it is possible to provide recommendations and define the scope of work for the migration.
E.g:
In-Scope
Environment Migration - AIS V6.6 to AC V3.7 on Premises
Set Up AC Environment with the latest version of Adeptia
Setup 2 new Non-Prod (Test and QA) non-clustered environments
Setup 1 new Prod clustered environment
Perform current solution migration from AIS to AC V3.7 on-premises
Assist with QA/UAT
Out-Scope
Current solution optimization is not part of the scope
...
c. Adeptia Backend, Logs, and quartz database need to be migrated from HSQL to Oracle as HSQL is not supported in AC
Recommended Adeptia Connect Infra:
TEST (Kernel & Webrunner on Same Instance) Non-Clustered | QA (Kernel & Webrunner on Same Instance) Non-Clustered | PROD - Non-Clustered Connect Server & Portal on Same Instance) |
---|---|---|
|
|
|