After you have created have created the dashboard design activity, you need to execute it to publish it as a Custom Dashboard. You can execute the activity dashboard design either from the Dashboard Design screen or from the Custom Dashboard screen. 

Executing Activity from the Dashboard Design 

To execute from the

...

Design screen:

  1. Click Configure > CUSTOM DASHBOARD Design.
  2. Under Action, click MoreImage Addedarrow and then click Execute for the design you want to execute. 
    A new browser tab opens displaying the components that was chosen while creating the Dashboard Design activity.

...

  1. Select the refresh time from the Select refresh delay (in seconds) to configure the refresh time. 

To execute from the

...

Custom Dashboard screen:

  1. Go to Monitor > Dashboard > Custom Dashboardto the Dashboard page.
  2. Click Custom Dashboard icon in the left pane.
  3. Click to the activity design to execute. 
    A Dashboard applet appears new browser tab opens displaying the component components that was chosen while creating the Dashboard Design activity.
    Image Removed
    Image Added
  4. Select the refresh time from the Select refresh delay (in seconds) to configure the refresh time. 9