About this task
While designing a process flow you can set the priority for it in Process Flow Properties. This helps you run the process flows based on the priority order you set for them. For example, a process flow defined with High priority is executed first followed by the one with Medium priority and then the remaining ones with Low priority.
To know more about process flow execution based on priority, click here.
Procedure
Follow the steps below to set the priority:
Click View Process Flow Properties icon on the Toolbar.
Select the priority order from in the Process Flow Priority drop-down list field.
Click outside of the Properties window to save the setting.